Construction Info
​
Provided below is current construction information on the upcoming construction schedule, but please remember schedules can be impacted by a variety of factors to include weather, materials scheduling, availability of resources, and coordination with others.
​
Current Construction Info (Sept. 25, 2024):
​
Please note that bridge construction is in full operation and this area is an active construction zone. There are many hazards for those walking or traveling near the work zone, so please stay away from this area. To maintain safety, the contractor has installed additional signage around the area. Crews across the city begin work at 6 a.m. annually, April through October due to increasing temperatures.
Work continues with asphalt paving activities scheduled this week. To accommodate paving. slurry seal and striping activities, the following restrictions are in place through Monday, September 30:
-
Happy Valley Road is closed to travel between Hayden Road and Miller Road through September 30. Detour signage is in place to direct travelers around the closure.
-
Miller Road is closed just south of Mariposa Grande also through September 30, for paving and striping activity.
-
Parkview Lane is closed at Miller Road through September 30. During this time, there is no access to/from Miller Road at Parkview Lane. Pinnacle Peak Reserve residents may use Juan Tabo Road to access Miller Road during this time.
Scheduled to begin the week of Sept. 30 for approximately 3-4 weeks, crews will install the decorative pedestrian fence along the bridge, as stone veneer work along the bridge also continues.
Concrete crews and landscape crews continue work in the project area through October to conduct remaining concrete work, and landscape installation.
​Thank you for your patience during this work.